Case Study: Data Centre Migration for Global Healthcare Technology Organisation

Sunspeed delivered the end-to-end migration of customer infrastructure supporting footprint consolidation and enabling future expansion. 

Background

A global healthcare technology organisation required the migration and consolidation of infrastructure within an existing data centre environment. The objective was to reduce cabinet footprint, improve cable management, and prepare the platform for future growth, while maintaining service continuity. 

The project involved the relocation of 160 devices, with consolidation into eight new cabinets and a planned cutover aligned to a fixed operational window.

160 x

Devices relocated.

The CHALLENGE

The client’s environment had evolved over time, resulting in fragmented rack layouts and inconsistent cabling. This created operational overhead, limited visibility, and made future expansion difficult.

The migration needed to address several priorities simultaneously. Services had to remain stable throughout the transition. Existing connectivity required full validation. New cabling needed to be installed ahead of the move. The team also had to work within a live data centre environment with limited access windows and strict change controls.

Each device was connected via multiple network and power paths, with an estimated average of four cables per device requiring end to end tracing. This introduced risk around mispatching, service interruption, and incomplete documentation if not handled methodically.

0hrs

Unplanned downtime.

OUR Solution

The engagement began with a detailed discovery phase. Existing rack elevations were reviewed and validated on site. Engineers completed physical cable tracing for each device, confirming connectivity and documenting source to destination mappings. This produced an accurate patch schedule that became the foundation for the migration plan.

The team executed the migration during the agreed change window. Devices were disconnected, transported within the facility, installed into the new cabinet layout, and repatched according to the validated schedule. Each stage was sequenced to minimise service impact and maintain logical groupings.The migration followed a phased cutover model. Devices were grouped by dependency and relocated in controlled batches.

The process for each batch included:

  • Disconnect and verification
  • Physical relocation within the data centre
  • Rack installation in the new cabinets
  • Patching to pre installed cabling
  • Connectivity validation

OUTCOMES

The client achieved consolidation from the existing footprint into eight cabinets, improving density and creating space for future expansion. Cable management was significantly improved, reducing complexity and enabling faster troubleshooting. Documentation produced during the engagement provided a clear and accurate reference for ongoing operations.

Additional outcomes included:

  • Improved airflow and cabinet organisation
  • Reduced cable congestion and clearer routing
  • Validated connectivity across all migrated devices
  • Enhanced operational visibility through updated patch schedules

DISCOVER HOW WE CAN SUPPORT YOU

Sunspeed has been providing IT services for over 30 years. We are industry leaders in transformation projects such as Data Centre Relocations, and provide a comprehensive package of services to deliver you control of your physical IT infrastructure. Reach out today to discover how we can support you:

"The client also stated that the install, device positioning and implementation was the best he has ever seen put out in production from rolling out their solutions"

Sam
Business Development Manager

"Mission focussed and attacked the task professionally, great communication between the guys (and me) when anything needed to be checked. All eventualities were accounted for."

Laura
Project Manager

"The entire Sunspeed team demonstrated professionalism throughout and the standards achieved were high, exceeding my expectations, which were by no means low!"

Paul
IT Project Manager

"Thank you once again for your help, collaboration, and support throughout the entire project, while ensuring no impact to our stakeholders."

Martin
IT Project Manager

"The office clearance and Data Centre recovery went like clockwork. All work was carried out in an efficient and professional manner and no problems, great!"

Andrew
IT Project Manager

"Hi Sunspeed just wanted to say all delivered yesterday safe and sound. And big thanks to the team you guys are rock stars..."

Jackie
Solutions Centre Manager