Overview:
Sunspeed was engaged by a Data Centre partner to conduct the installation of 56 x devices & 300 SFPs into a customer racks, and the connect & dress of over 450 x cables. Sunspeed provided an end-to-end process, including: Assembling devices where required (fit correct PSU, drives, cards etc); Fitting rails & rack mounting kits as provided; Fitting devices to allocated rack unit position as per provided rack diagram; Recording & verifying serial number to device & rack unit location mapping; Recording & verifying power rail socket number to device mapping identifier for A & B feeds; Powering on devices; Confirming power on self-test functionality (POST); Labeling devices with host name; Re-packaging dead-on-arrival (DOA) or unrepairable hardware for return-merchandize-authorisation (RMA); Connecting & dressing all in-rack cables.

THE PROJECT
Hardware Installation
Sunspeed managed the full installation process including power-up and testing.
Connect & Dress
Our team connected and dressed all in-rack cabling.
DOA testing
Sunspeed conducted a thorough DOA test of hardware and repackaged unrepairable hardware.
Labelling
Sunspeed printed and applied labels to all devices & labels.

Spotlight: End-to-End Solution
Sunspeed provides a full end-to-end solution for the deployment of IT equipment to Data Centre or comms room environments. We can: Store equipment in our secure warehouse -> Consolidate orders and unpack/prepare devices for delivery -> Provide staging services to pre-load or configure devices in our specialist build rooms -> Design & Install structured cabling to prepare racks for new equipment ->Provide Final Mile Deliveries with our secure transport capability and specialist IT-spec vehicles -> Install & cable devices in customer environments -> Provide ongoing management & smart hands maintenance -> Decommission and dispose of redundant assets.