End-to-End Relocation – Japan

Overview

Sunspeed partnered with McCollister’s to deliver a data centre relocation of 45 x devices in Tokyo, Japan. We implemented a full end-to-end solution including a hardware and end-to-end cable trace audit, pre-cable, relocation and connect & dress, as-well as a Technical Project Management overlay. Our team delivered key Technical Design deliverables including the design of source and destination rack plans and patching schedules and management of our bespoke infrastructure planner tool. With the support of McCollister’s, we managed to successfully navigate numerous challenges including cable mapping issues and shifting timescales.

Data Centre Audit Engineer.

THE PROJECT

Technical Design

Sunspeed used audit data to create destination rack plans and patching schedules to plan the migration and connect & dress.

Goods-in-Transit Insurance

Sunspeed provided the customer with industry-leading goods-in-transit insurance cover.

Full Technical Audit

Sunspeed captured key rack-elevation and connectivity information to enable migration planning exercises.

Specialist Technical Transport

McCollister’s provided specialist transport to ensure equipment was transported safely and securely.
Physical Server Migration & IT Relocation
Sunspeed as partner
Sunspeed’s real value lies in our ability to provide specialist resources and expertise to sit around the service offerings of our partners and deliver maximum value to end-customers. Our services encompass the full physical IT lifecycle, and we can manage the physical management of equipment from installs, through moves and changes, to end of life and ITAD. We help our partners stay ‘sticky’ with their customers, and ensure they are taken care of at every step of their journey.

"The client also stated that the install, device positioning and implementation was the best he has ever seen put out in production from rolling out their solutions"

Sam
Business Development Manager

"Mission focussed and attacked the task professionally, great communication between the guys (and me) when anything needed to be checked. All eventualities were accounted for."

Laura
Project Manager

"The entire Sunspeed team demonstrated professionalism throughout and the standards achieved were high, exceeding my expectations, which were by no means low!"

Paul
IT Project Manager

"Thank you once again for your help, collaboration, and support throughout the entire project, while ensuring no impact to our stakeholders."

Martin
IT Project Manager

"The office clearance and Data Centre recovery went like clockwork. All work was carried out in an efficient and professional manner and no problems, great!"

Andrew
IT Project Manager

"Hi Sunspeed just wanted to say all delivered yesterday safe and sound. And big thanks to the team you guys are rock stars..."

Jackie
Solutions Centre Manager