Case studies

We operate in both the public and private sectors and work with organisations of all sizes. Whoever the client and whatever the size of the project, our care and attention to detail is exactly the same.

Virtual1 Data Centre Relocation – London to London.

97 devices relocated and reconnected over 7 migration events.

Full site surveys at both locations.
Full audit – 97 x devices. 1,200 x cable connections.
Technical Project Management – Delivery site rack plan and patching schedule design.
Full pre-cable ahead of the relocation – Supply and installation of 1,200 x cables.
Relocation on a de/re rack basis – 97 x devices.
Migration support to connect and dress all cables following the relocation.
Goods in Transit insurance cover.

University of Oxford Data Centre Relocation – Oxford to London.

64 devices relocated and reconnected over a single migration.

Full site surveys at both locations.
Verification audit.
Technical Project Management support.
Full pre-cable ahead of the relocation – Installation of 450 x cables.
Relocation on a de/re rack basis – 64 x devices.
Migration support to connect and dress all cables following the relocation.
Goods in Transit insurance cover.

New Hardware Installation for Leading Global Data Centre – London.

End to End Hardware Installation of 55 devices.

Full site survey.
Technical Project Management support.
Installation of 55 x devices and 432 x cables.

L&Q Data Centre Relocation – London to London.

88 devices relocated and reconnected in a single migration phase.

Full site surveys at both locations.
Full infrastructure audit – 88 x devices. 650 x cable connections.
Technical Project Management – Delivery site rack plan optimisation and patching schedule support.
Full pre-cable ahead of the relocation – Supply and installation of 650 x cables.
Relocation on a de/re rack basis – 88 x devices.
Migration support to connect and dress all cables following the relocation.
Goods in Transit insurance cover.

Choopa Data Centre Relocation – London to London.

280 devices relocated and reconnected in a single migration phase.

Full site surveys at both locations.
Full audit – 280 x devices. 1,100 x cable connections.
Technical Project Management – Delivery site rack plan and patching schedule design.
Full pre-cable ahead of the relocation – Supply and installation of 1,100 x cables.
Relocation on a de/re rack basis – 280 x devices.
Migration support to connect and dress all cables following the relocation.
Goods in Transit insurance cover.

Royal Mail Hardware Audit - UK Wide.

2,762 physical devices audited in 11 days.

RMG required this information to assist them with their high level planning for an IT consolidation project.
Royal Mail Group (RMG) engaged Sunspeed to complete a physical hardware audit of their main IT estate, which was spread across ten different Data Centre / Computer Room locations throughout the UK.